Program Management Professional (PgMP) — Question 329
A program manager will need to document the benefits sustainment plan after completion of a program. Which two actions should the program manager include in the plan? (Choose two.)
Answer options
- A. Include the business owner in the benefits realization process
- B. Align the expected benefits with the organization’s goals and objectives
- C. Monitor the benefits delivered by the program components.
- D. Identify and assess the value and impact of the program benefits
- E. Assign responsibility and accountability for benefits realization
Correct answer: A, E
Explanation
Including the business owner in the benefits realization process (A) ensures that the stakeholders are engaged and that the benefits are aligned with their expectations. Assigning responsibility and accountability for benefits realization (E) is crucial for ensuring that there is clear ownership of the benefits process. The other options, while important, do not directly relate to the actions that should be included in a benefits sustainment plan.