Program Management Professional (PgMP) — Question 314
The program components have been completed, and the program manager needs to capture and validate benefits delivery. What should the program manager do next?
Answer options
- A. Modify the program master schedule
- B. Consult the benefit management plan
- C. Update the program roadmap
- D. Review and update the benefit register
Correct answer: D
Explanation
The correct action is to review and update the benefit register, as it directly tracks the benefits delivered by the program. Modifying the master schedule or updating the roadmap does not specifically address the need to capture and validate benefits. Consulting the benefit management plan may provide guidance, but it does not fulfill the immediate requirement of updating the benefit register.