Program Management Professional (PgMP) — Question 28
Program manager B leaves the program and program manager A takes over the program responsibilities. Program manager A wants to ensure that all expected benefits of the program are realized.
What is used to assess the program cost/benefit justification?
Answer options
- A. Program charter
- B. Benefits management plan
- C. Program business case
- D. Program scope statement
Correct answer: C
Explanation
The correct answer is C, the Program business case, as it outlines the justification for the program, including the expected benefits and costs. The other options, such as the Program charter and Program scope statement, provide different aspects of the program, but do not specifically focus on the financial justification and benefits realization.