Program Management Professional (PgMP) — Question 271
What should a program manager do when a scope change has been approved that will drastically affect the program costs assuming that the costs will be added to the program budget?
Answer options
- A. Adjust the cost baseline
- B. Communicate cost of the change to all stakeholders
- C. Adjust the quality baseline
- D. Communicate the change to all stakeholders
Correct answer: A
Explanation
The correct answer is A, as adjusting the cost baseline is necessary to reflect the newly approved costs in the program budget. Options B and D involve communication but do not address the need for formal adjustments to budget documents, while option C incorrectly suggests changing the quality baseline, which is unrelated to cost changes.