Program Management Professional (PgMP) — Question 269
You are the program manager for your organization. You have created a program that will create things for the organization throughout the program not only at program closure. All of the following are elements that you may transfer to the organization throughout the program's life cycle except for which one?
Answer options
- A. Benefits
- B. Risk management outcomes
- C. Program personnel
- D. Outputs from team development
Correct answer: C
Explanation
The correct answer is C, as program personnel are typically not transferred during the program's life cycle but remain with the program until its completion. In contrast, benefits, risk management outcomes, and team development outputs can be realized and transferred incrementally throughout the program's duration.