Program Management Professional (PgMP) — Question 211

At what point in the project is the risk of failing to achieve the project objectives the greatest?

Answer options

Correct answer: C

Explanation

The risk of failing to achieve project objectives is highest at the project start because this is when uncertainties and unknowns are most prevalent. As the project progresses through planning and execution, risks can be identified and mitigated. By the end of the project, most objectives have typically been defined and addressed.