Program Management Professional (PgMP) — Question 200

You are the program manager of a new program in your organization. This program will last for one year and your program team will work full-time on the effort.
The nature of the work requires that the program team work closely together for the next year, but many of the program team members have never met one another. You decide to take the team on an outing where they can work together through challenges, learn teamwork, and get to know one another. This is an example of what process?

Answer options

Correct answer: D

Explanation

The correct answer is D, Team development, as the outing is aimed at enhancing collaboration and building relationships among team members. Options A, B, and C do not accurately represent the focus on improving team dynamics and cohesion through shared experiences and teamwork activities.