You are the program manager of the JNH Program. Tom, a project manager in your program, has just completed his project and is ready to officially close his project. You agree that Tom's project is completed. What role do you play in Tom's project closure?

Answer options

Correct answer: B

Explanation

The correct answer is B because as the program manager, your responsibility includes ensuring that all projects within the program are closed appropriately at the project level. Option A is incorrect as it focuses on the project sponsor rather than the program manager's role, while C and D incorrectly imply direct closure responsibilities that are not solely yours.