Program Management Professional (PgMP) — Question 179

Near the end of an ongoing project, the program manager is terminated due to underperformance and a new program manager joins the team. The program's last component project will go live in one week.
What must the new program manager do before program closure?

Answer options

Correct answer: D

Explanation

The correct answer is D because it is crucial for the new program manager to clarify responsibilities for benefits sustainment and establish success metrics before closing the program. Option A is incorrect as it focuses on past evaluations rather than future responsibilities. Option B prematurely seeks closure without ensuring all aspects are addressed. Option C, while important, does not prioritize the identification of benefits sustainment responsibilities.