Program Management Professional (PgMP) — Question 143

What actions are taken in the process of developing and maintaining a program risk register?

Answer options

Correct answer: B

Explanation

Option B is correct because it emphasizes the need to identify the root cause of potential risks, which is essential for effective risk management. The other options, while highlighting important aspects of risk management, do not focus on identifying root causes, which is critical for addressing risks effectively.