Program Management Professional (PgMP) — Question 141
Program A is dependent upon program B to complete benefits sustainment for two benefits. Program A is on track to meet program benefits. However, program
B's program manager has just advised that program B has been closed.
What should program A's program manager update and review first with the stakeholders?
Answer options
- A. Benefits sustainment plan
- B. Benefits register
- C. Benefits management plan
- D. Benefits transition plan
Correct answer: A
Explanation
The benefits sustainment plan is crucial because it directly outlines how the benefits will be maintained following the closure of Program B. The other options, while important, do not specifically address the immediate impact of Program B's closure on the benefits that Program A is trying to sustain.