Program Management Professional (PgMP) — Question 118
A program manager recognizes that a successful resource being used in project A could also be used in project B.
What should the program manager do first to leverage the utilization of this resource?
Answer options
- A. Assign project A's resource to project B.
- B. Reassign the resource to project B after project A ends.
- C. Prioritize the resource to optimize their use across both projects A and B.
- D. Mitigate risk by leveraging other resources in project A.
Correct answer: B
Explanation
The correct answer is B because it ensures that the resource is fully utilized in project A before being assigned to project B, preventing disruption. Options A and C suggest reallocating or prioritizing the resource prematurely, which could negatively impact project A. Option D does not leverage the identified resource effectively.