Program Management Professional (PgMP) — Question 118

A program manager recognizes that a successful resource being used in project A could also be used in project B.
What should the program manager do first to leverage the utilization of this resource?

Answer options

Correct answer: B

Explanation

The correct answer is B because it ensures that the resource is fully utilized in project A before being assigned to project B, preventing disruption. Options A and C suggest reallocating or prioritizing the resource prematurely, which could negatively impact project A. Option D does not leverage the identified resource effectively.