Program Management Professional (PgMP) — Question 111

Which of the following documents sets the project objectives?

Answer options

Correct answer: A

Explanation

The Project charter is the document that defines the project's objectives and overall goals. The Project schedule outlines timelines and milestones, the Project scope statement details the work required, and the Project organization chart shows the hierarchy within the project team.