Program Management Professional (PgMP) — Question 108
You are the program manager for your organization and you're coaching Tom, an aspiring program manager, on program management. Tom is curious about controlling communications. Which one of the following is an output of the communications control process?
Answer options
- A. Approved change requests
- B. Communications management plan
- C. Stakeholder analysis charts
- D. Performance reports
Correct answer: D
Explanation
Performance reports are generated as part of the communications control process, providing insights on project status and stakeholder engagement. The other options, while related to program management, do not specifically result from the communications control process, as they pertain to different aspects of project management.