Program Management Professional (PgMP) — Question 104

When should a program manager approve the closure of a component project?

Answer options

Correct answer: A

Explanation

The correct answer is A because the closure of a component project should only happen once the acceptance criteria have been fulfilled, ensuring all necessary requirements are satisfied. Options B, C, and D do not necessarily ensure that the project has met all specified criteria for acceptance, which is critical for officially closing the project.