Portfolio Management Professional (PfMP) — Question 52
The portfolio steering committee has authorized the addition of two new portfolio components and the termination of one existing component. A tool or function that supports the communication process resulting from this change is a portfolio:
Answer options
- A. component categorization meeting.
- B. governance board.
- C. management information system.
- D. resource management planning session.
Correct answer: A
Explanation
The correct answer is A, as a component categorization meeting specifically focuses on discussing and communicating changes related to portfolio components. The governance board (B) oversees overall governance but is not specifically for communication of changes, the management information system (C) manages data but does not facilitate communication, and the resource management planning session (D) is focused on resource allocation rather than component changes.