Portfolio Management Professional (PfMP) — Question 44

Which of the following are the tools and techniques for “Develop Portfolio Performance Management Plan”? (Choose two.)

Answer options

Correct answer: B, D

Explanation

The correct answers, B (Capability and Capacity Analysis) and D (PMIS), are essential for developing a Portfolio Performance Management Plan as they provide the necessary insights and data management capabilities. Options A and C, while useful in other contexts, do not specifically pertain to the tools and techniques used for this particular planning process.