Portfolio Management Professional (PfMP) — Question 36
The portfolio performance management plan should include:
Answer options
- A. portfolio goals and strategies, performance measurement tactics, and the portfolio governance model.
- B. anticipated benefit realization, target dates, and the earned value of components.
- C. resource utilization, resource gaps, and performance metrics.
- D. performance roles and responsibilities, metrics, and the reporting process.
Correct answer: D
Explanation
The correct answer, D, is accurate because it highlights the importance of defining roles and responsibilities, establishing metrics, and outlining the reporting process within the portfolio performance management plan. Options A, B, and C are relevant to other aspects of project management but do not specifically address the components necessary for effective performance management in a portfolio context.