Portfolio Management Professional (PfMP) — Question 3
Which of the following are the input of “Optimize Portfolio”? (Choose two.)
Answer options
- A. Portfolio Strategic Plan
- B. Portfolio Process Assets
- C. Portfolio Charter
- D. Portfolio Reports
Correct answer: B, D
Explanation
The correct inputs for the 'Optimize Portfolio' process are 'Portfolio Process Assets' and 'Portfolio Reports', as they provide essential data and insights needed for optimization. The 'Portfolio Strategic Plan' and 'Portfolio Charter' are important documents but do not serve as inputs in this specific process.