Portfolio Management Professional (PfMP) — Question 15
After developing a portfolio strategic plan, you create various portfolio scenarios using different combinations of both potential components and current components, evaluating their possible outcomes based on multiple assumptions? Which process are you doing?
Answer options
- A. Develop Portfolio Charter
- B. Optimize Portfolio
- C. Develop Portfolio Roadmap
- D. Manage Strategic Change
Correct answer: A
Explanation
The correct answer is 'Develop Portfolio Charter' because this process involves outlining and establishing the framework for the portfolio, including scenarios. The other options do not focus on the creation of scenarios and their evaluations; 'Optimize Portfolio' is about improving components, 'Develop Portfolio Roadmap' entails planning future actions, and 'Manage Strategic Change' involves handling transitions rather than scenario evaluation.