Portfolio Management Professional (PfMP) — Question 13
Which of the following should be included in a portfolio risk management plan? (Choose two.)
Answer options
- A. Dependencies
- B. Methodology
- C. Roles and responsibilities
- D. Key milestones and deliverables
Correct answer: B, C
Explanation
The correct answers, B (Methodology) and C (Roles and responsibilities), are crucial as they define the approach to managing risks and the individuals involved in the process. Options A and D, while important for project management, do not specifically pertain to the risk management aspect of a portfolio.