Certified Associate in Project Management (CAPM) — Question 95

A computer application development project is almost closing. The project manager uses a document comprised of a checklist that requires a formal feature-to-feature approval in order to demonstrate compliance with the customer's specifications.

Which document is the project manager using?

Answer options

Correct answer: A

Explanation

The correct answer is A, as the acceptance test procedure is specifically used to validate that the application meets the agreed-upon specifications. The other options do not serve the same purpose; B refers to versioning processes, C pertains to deliverables rather than approvals, and D involves ceremonies rather than formal compliance checks.