Certified Associate in Project Management (CAPM) — Question 84

Which three of the following should a project manager consider when customizing a project communications management plan? (Choose three.)

Answer options

Correct answer: B, C, D

Explanation

The correct options B, C, and D are essential considerations for effective communication, as they address how information will be shared (methods), where stakeholders are located (physical location), and the various parties involved (internal and external stakeholders). Option A, while relevant, doesn't directly impact the customization of the communications management plan, and option E is too specific to the sponsor rather than the broader stakeholder communication needs.