Certified Associate in Project Management (CAPM) — Question 82

What should be completed when the work-in-progress (WIP) limit is reached and new work has been requested?

Answer options

Correct answer: B

Explanation

The correct answer is B because when the WIP limit is reached, it's essential to manage new requests by putting them in a holding area until capacity allows for their consideration. Options A and D suggest adding work immediately, which contradicts the WIP limit principle, while C does not address the immediate need to manage the new request.