Certified Associate in Project Management (CAPM) — Question 69

A few project team members are having issues understanding the requirements as described. Which action should be taken to resolve this issue?

Answer options

Correct answer: B

Explanation

The correct answer is B because it focuses on reviewing the requirements traceability matrix, which is directly related to understanding requirements, and facilitates a meeting with the business analyst and key stakeholders to clarify any confusion. Option A is incorrect as it adds unnecessary steps by including the business analysis communications management plan, while options C and D do not prioritize the requirements traceability matrix, which is key to addressing the understanding issues.