A project team is closing out a phase and updating the organizational knowledge base. What organizational process asset (OPA) will the team update?
Answer options
- A. Traceability matrices
- B. Lessons learned
- C. Change control procedures
- D. Resource availability
Correct answer: B
Explanation
The correct answer is B, as 'Lessons learned' documents the experiences and insights gained during the project phases, which is crucial for improving future projects. The other options, such as 'Traceability matrices', 'Change control procedures', and 'Resource availability', do not specifically focus on capturing and updating knowledge from completed phases.