Certified Associate in Project Management (CAPM) — Question 55
What earned value (EV) measure indicates the cost efficiency of the work completed?
Answer options
- A. Cost variance (CV)
- B. Cost performance index (CPI)
- C. To-complete performance index (TCPI)
- D. Variance at completion (VAC)
Correct answer: B
Explanation
The Cost Performance Index (CPI) measures the cost efficiency of the work accomplished, indicating how much value is earned for each dollar spent. Cost variance (CV) provides a dollar amount of cost performance but does not directly measure efficiency, while the To-complete performance index (TCPI) and Variance at completion (VAC) focus on future performance and overall project completion costs, respectively.