Certified Associate in Project Management (CAPM) — Question 452
Which of the following are outputs of the Define Scope process in Project Scope Management?
Answer options
- A. Requirements documentation and requirements traceability matrix
- B. Scope management plan and requirements management plan
- C. Project scope statement and project documents updates
- D. Scope baseline and project documents updates
Correct answer: C
Explanation
The correct answer is C, as the Define Scope process specifically results in the creation of the project scope statement and updates to project documents. Options A and B refer to documentation related to requirements but are not direct outputs of the Define Scope process, while option D includes scope baseline but does not specify the key outputs generated.