Certified Associate in Project Management (CAPM) — Question 44
Which tool should a project manager consider to deal with multiple sources of risk?
Answer options
- A. An updated risk register
- B. Risk breakdown structure
- C. Issue log
- D. Stakeholder register
Correct answer: B
Explanation
The Risk breakdown structure (B) is specifically designed to categorize and manage risks from various sources, making it the most suitable choice. An updated risk register (A) is useful for tracking risks but does not provide the same structured approach as a breakdown structure. An issue log (C) is meant for tracking project issues rather than risks, and a stakeholder register (D) focuses on stakeholders rather than risk management.