Certified Associate in Project Management (CAPM) — Question 436

A functional manager is delegating a key project to a project team without a project manager. Which communication method will be most effective?

Answer options

Correct answer: A

Explanation

The interactive communication method is most effective in this scenario because it allows for real-time feedback and discussions, which are crucial when there is no designated project manager. The other methods, such as push communication, may not facilitate immediate clarification and engagement, while verbal and oral options could be less effective without the structured interaction that ensures understanding among team members.