Certified Associate in Project Management (CAPM) — Question 429
A project manager is launching an information system to provide a lessons learned database. This action is necessary for recipients to access content at their own discretion. Which communication method is described?
Answer options
- A. Push communication
- B. Pull communication
- C. Interactive communication
- D. Stakeholder communication
Correct answer: B
Explanation
The correct answer is B, Pull communication, as it allows users to access information at their convenience. Push communication involves sending information to recipients without their active retrieval, while interactive communication requires real-time engagement. Stakeholder communication is broader and does not specifically refer to the method of accessing information.