Certified Associate in Project Management (CAPM) — Question 42
Due to organizational changes, a new product owner joins a project. The product owner wants to review the process used to obtain team members, facilities, equipment, materials, supplies, and other resources necessary to complete project work.
What process should the project manager review with the product owner?
Answer options
- A. Acquire Resources
- B. Plan Resource Management
- C. Estimate Activity Resources
- D. Control Resources
Correct answer: A
Explanation
The correct answer is A, Acquire Resources, as this process specifically focuses on obtaining the necessary resources for project work. The other options do not directly involve the act of acquiring resources: B relates to planning management strategies, C involves estimating the types and quantities of resources required, and D deals with monitoring and managing resources that have already been acquired.