Certified Associate in Project Management (CAPM) — Question 417
What are the objectives of initiation processes?
Answer options
- A. Initiation processes are performed in order to develop the project charter and identify stakeholders.
- B. Initiation processes are performed in order to obtain budget approval for a project or phase and approve scope with customers.
- C. Initiation processes are performed to identify business objectives for a project or phase and identify stakeholders' goals.
- D. Initiation processes are performed to map initial requirements for a project or phase and prioritize them with stakeholders.
Correct answer: A
Explanation
The correct answer is A because initiation processes primarily focus on developing the project charter and identifying stakeholders, which are essential first steps in project management. Options B, C, and D describe activities that occur later in the project life cycle, such as budget approval and requirement mapping, rather than the core objectives of initiation.