Responsible, accountable, consult and inform (RACI) is an example of which of the following?
Answer options
- A. Text-oriented format
- B. Resource management plan
- C. Organization chart
- D. Responsibility assignment matrix (RAM)
Correct answer: D
Explanation
The correct answer is D, as a Responsibility Assignment Matrix (RAM) specifically outlines roles and responsibilities, which is exactly what the RACI model does. Options A, B, and C do not accurately describe what RACI represents, as they refer to different aspects of project management and organization.