Certified Associate in Project Management (CAPM) — Question 411

Responsible, accountable, consult and inform (RACI) is an example of which of the following?

Answer options

Correct answer: D

Explanation

The correct answer is D, as a Responsibility Assignment Matrix (RAM) specifically outlines roles and responsibilities, which is exactly what the RACI model does. Options A, B, and C do not accurately describe what RACI represents, as they refer to different aspects of project management and organization.