Certified Associate in Project Management (CAPM) — Question 405
What are the inputs of the Estimate Costs process?
Answer options
- A. Project management plan, work performance data, enterprise environmental factors, and organizational process assets
- B. Project management plan, project documents, enterprise environmental factors, and organizational process assets
- C. Cost baseline, enterprise environmental factors, benefits management plan, and organizational process assets
- D. Project management plan, enterprise environmental factors, basis of estimates, and organizational process assets
Correct answer: B
Explanation
The correct answer is B because it includes the project management plan and project documents, which are essential for estimating costs. Options A, C, and D include elements that are not directly relevant to the Estimate Costs process, such as work performance data and cost baseline, which do not serve as inputs for this specific process.