Certified Associate in Project Management (CAPM) — Question 401

Which task will a project manager undertake while conducting Project Resource Management?

Answer options

Correct answer: D

Explanation

The correct answer is D, as defining roles and responsibilities is a key aspect of resource management, ensuring that each team member knows their tasks. Options A, B, and C, while important to project management, focus on other areas such as resource control, procurement, and training, rather than clearly outlining team member roles.