Certified Associate in Project Management (CAPM) — Question 396
Which are examples of processes that may be used once or at predefined points in the project life cycle?
Answer options
- A. Develop Project Charter and Close Project or Phase
- B. Define Activities and Acquire Resources
- C. Control Schedule and Conduct Procurements
- D. Monitor Communications and Control Costs
Correct answer: A
Explanation
The correct answer is A because both 'Develop Project Charter' and 'Close Project or Phase' are processes that occur once or at specific milestones in the project life cycle. In contrast, options B, C, and D include processes that are typically repeated throughout the project, such as defining activities, controlling schedules, and monitoring communications.