Certified Associate in Project Management (CAPM) — Question 396

Which are examples of processes that may be used once or at predefined points in the project life cycle?

Answer options

Correct answer: A

Explanation

The correct answer is A because both 'Develop Project Charter' and 'Close Project or Phase' are processes that occur once or at specific milestones in the project life cycle. In contrast, options B, C, and D include processes that are typically repeated throughout the project, such as defining activities, controlling schedules, and monitoring communications.