Certified Associate in Project Management (CAPM) — Question 383
A project it just beginning, and management creates a long list of potential stakeholders. Which statement about identifying and engaging stakeholders is correct?
Answer options
- A. The project manager should identify and deal with stakeholders only during the execution phase.
- B. Stakeholder satisfaction should be identified immediately and managed as a project objective.
- C. The project manager should focus on project objectives and deal with stakeholders as a secondary priority.
- D. Stakeholder satisfaction is the most important goal, and project objectives should be considered a secondary priority.
Correct answer: B
Explanation
The correct answer is B because stakeholder satisfaction is crucial from the beginning of the project and should be actively managed as a project objective. Options A and C are incorrect as they suggest delaying stakeholder engagement until later phases, which can lead to unmet expectations. Option D incorrectly prioritizes stakeholder satisfaction over project objectives, which can jeopardize the project's success.