Certified Associate in Project Management (CAPM) — Question 383

A project it just beginning, and management creates a long list of potential stakeholders. Which statement about identifying and engaging stakeholders is correct?

Answer options

Correct answer: B

Explanation

The correct answer is B because stakeholder satisfaction is crucial from the beginning of the project and should be actively managed as a project objective. Options A and C are incorrect as they suggest delaying stakeholder engagement until later phases, which can lead to unmet expectations. Option D incorrectly prioritizes stakeholder satisfaction over project objectives, which can jeopardize the project's success.