Certified Associate in Project Management (CAPM) — Question 376
In an adaptive or agile life cycle, how are the customer and sponsor involved in the project scope management activities?
Answer options
- A. Involvement is needed only during project initiation
- B. Minimal involvement of stakeholders is sufficient
- C. They should be continuously engaged
- D. They should be involved only during phase or deliverable reviews
Correct answer: C
Explanation
The correct answer is C because continuous engagement of the customer and sponsor is essential in adaptive or agile environments to ensure that the project aligns with their needs and expectations. The other options suggest limited or infrequent involvement, which could lead to misalignment and potential project failure.