Certified Associate in Project Management (CAPM) — Question 367
The project manager is working in the processes of Project Resource Management. Which process is the project manager developing if they are using parametric estimation?
Answer options
- A. Plan Resource Management
- B. Estimate Activity Resources
- C. Estimate Costs
- D. Acquire Resources
Correct answer: B
Explanation
The correct answer is B, as parametric estimation is a method used specifically in the Estimate Activity Resources process to determine the types and quantities of resources needed. Options A, C, and D relate to different aspects of resource management, such as planning, cost estimation, and acquiring resources, but do not directly involve the estimation of activity resources.