Which two processes should be used to influence costs in the early stages of a project?
Answer options
- A. Estimate Costs and Determine Budget
- B. Plan Cost Management and Estimate Activity Durations
- C. Control Quality and Control Costs
- D. Plan Stakeholder Engagement and Plan Communications Management
Correct answer: A
Explanation
The correct answer, A, focuses on estimating costs and determining the budget, which are critical early processes for controlling project expenses. Options B, C, and D do not directly address cost influence at the project's outset; B pertains to planning and scheduling, C is about monitoring quality and costs post-planning, and D relates to stakeholder and communication management.