Certified Associate in Project Management (CAPM) — Question 352
Which set of activities should a project manager use as part of the Develop Team process?
Answer options
- A. Training and establishing ground rules
- B. Networking activities and estimating team resources
- C. Conflict management activities and tracking team performance
- D. Recruit new team members and training
Correct answer: A
Explanation
The correct answer is A because training and establishing ground rules are essential for fostering a collaborative team environment. Options B, C, and D focus on different aspects of team management but do not directly pertain to the specific activities involved in the Develop Team process.