Certified Associate in Project Management (CAPM) — Question 352

Which set of activities should a project manager use as part of the Develop Team process?

Answer options

Correct answer: A

Explanation

The correct answer is A because training and establishing ground rules are essential for fostering a collaborative team environment. Options B, C, and D focus on different aspects of team management but do not directly pertain to the specific activities involved in the Develop Team process.