Certified Associate in Project Management (CAPM) — Question 35
What does expert judgement provide as an input to the resource management plan?
Answer options
- A. Geographic distribution of facilities and resources
- B. Physical resource management policies and procedures
- C. Estimated lead times based on lessons learned
- D. Templates for the resource management plan
Correct answer: C
Explanation
Expert judgement provides valuable insights based on previous experiences, which include estimated lead times that can be derived from lessons learned. The other options, while relevant to resource management, do not specifically relate to the insights gained from expert judgement.