Certified Associate in Project Management (CAPM) — Question 338
Which tools and techniques should a project manager use to monitor risks?
Answer options
- A. Expert judgment, data analysis, and interpersonal and team skills
- B. Data analysis, audits, and meetings
- C. Expert judgment, audits, and decision making
- D. Meetings, data gathering, and expert judgment
Correct answer: B
Explanation
The correct answer, B, includes tools specifically geared towards risk monitoring such as data analysis for trends, audits for compliance, and meetings to facilitate communication. Options A, C, and D contain valuable skills and tools, but they are not as directly focused on the continuous monitoring aspect required for effective risk management.