Certified Associate in Project Management (CAPM) — Question 338

Which tools and techniques should a project manager use to monitor risks?

Answer options

Correct answer: B

Explanation

The correct answer, B, includes tools specifically geared towards risk monitoring such as data analysis for trends, audits for compliance, and meetings to facilitate communication. Options A, C, and D contain valuable skills and tools, but they are not as directly focused on the continuous monitoring aspect required for effective risk management.