Certified Associate in Project Management (CAPM) — Question 336
In a project using agile methodology, who may perform the quality control activities?
Answer options
- A. A group of quality experts at specific times during the project
- B. The project manager only
- C. All team members throughout the project life cycle
- D. Selected stakeholders at specific times during the project
Correct answer: C
Explanation
The correct answer is C because in agile methodology, quality control is a shared responsibility, and all team members engage in activities to ensure quality throughout the project. Options A and D limit the scope of quality control to specific groups or times, while option B restricts it to the project manager, which is not in line with agile principles of collaboration.