Certified Associate in Project Management (CAPM) — Question 333

After defining activities in project schedule management, which processes should a project manager follow?

Answer options

Correct answer: A

Explanation

The correct answer is A because sequencing activities is essential to establish the order of tasks, followed by estimating their durations to ensure proper planning. Options B and C include processes that occur later in the project management timeline, while D introduces an irrelevant step of reviewing activities before scheduling.