Certified Associate in Project Management (CAPM) — Question 333
After defining activities in project schedule management, which processes should a project manager follow?
Answer options
- A. Sequence Activities and Estimate Activity Durations
- B. Estimate Activity Durations and Control Schedule
- C. Develop Schedule and Control Schedule
- D. Review Activities and Develop Schedule
Correct answer: A
Explanation
The correct answer is A because sequencing activities is essential to establish the order of tasks, followed by estimating their durations to ensure proper planning. Options B and C include processes that occur later in the project management timeline, while D introduces an irrelevant step of reviewing activities before scheduling.