Certified Associate in Project Management (CAPM) — Question 327

The project manager implemented the stakeholder engagement plan and realized that some updates should be made. Which components of the project management plan should be modified?

Answer options

Correct answer: C

Explanation

The correct answer is C because the stakeholder engagement plan directly relates to how information is communicated to stakeholders, making the communications management plan a relevant component to update. The project charter and risk management plan are less directly linked to stakeholder engagement, while the project charter and communications management plan do not specifically address the need for stakeholder engagement updates.