The project manager implemented the stakeholder engagement plan and realized that some updates should be made. Which components of the project management plan should be modified?
Answer options
- A. Project charter and stakeholder engagement plan
- B. Risk management plan and stakeholder engagement plan
- C. Communications management plan and stakeholder engagement plan
- D. Project charter and communications management plan
Correct answer: C
Explanation
The correct answer is C because the stakeholder engagement plan directly relates to how information is communicated to stakeholders, making the communications management plan a relevant component to update. The project charter and risk management plan are less directly linked to stakeholder engagement, while the project charter and communications management plan do not specifically address the need for stakeholder engagement updates.