Certified Associate in Project Management (CAPM) — Question 320
Which statement about identification and engagement of stakeholders during a project is correct?
Answer options
- A. Project stakeholders should be identified and engaged in every phase of the project to influence the success of the project directly.
- B. Project stakeholders should be identified and engaged once the prototype is completed to provide their feedback but refrain from making inputs during the project.
- C. Project stakeholders should be identified when the project charter is being completed and engaged during requirements gathering.
- D. Project stakeholders should be identified and engaged during requirements elicitation but not during the Define Scope process
Correct answer: A
Explanation
The correct answer is A because involving stakeholders throughout all phases is crucial for guiding the project towards success. The other options suggest limited engagement, which can hinder the project's ability to adapt and meet stakeholder needs effectively.