Certified Associate in Project Management (CAPM) — Question 318
Which group of inputs will a project manager use during the Monitor Stakeholder Engagement process?
Answer options
- A. Project charter, business documents, and project management plan
- B. Agreements, scope baseline, and project management plan
- C. Project charter, business case, and project management plan
- D. Work performance data, enterprise environmental factors, and project management plan
Correct answer: D
Explanation
The correct answer is D because the Monitor Stakeholder Engagement process relies on work performance data, which provides insights into stakeholder interactions, along with enterprise environmental factors that can affect engagement. The other options do not include work performance data, which is crucial for this specific process.