Certified Associate in Project Management (CAPM) — Question 315

Which of the following tasks is related to the Perform Qualitative Risk Analysis process?

Answer options

Correct answer: D

Explanation

The correct answer, D, is accurate because it involves prioritizing project risks and assessing their probability and impact, which are key components of the Perform Qualitative Risk Analysis process. Option A focuses on identifying risks without prioritization, B is about sensitivity analysis, and C deals with numerical data analysis rather than qualitative assessment.