Certified Associate in Project Management (CAPM) — Question 315
Which of the following tasks is related to the Perform Qualitative Risk Analysis process?
Answer options
- A. Identify the project risks and assign a probability of occurrence
- B. Perform a sensitivity analysis to determine which risk has the most potential for impacting the project
- C. Analyze the effect of identified project risks as numerical data
- D. Prioritize each protect risk and assign the probability of occurrence and impact for each one
Correct answer: D
Explanation
The correct answer, D, is accurate because it involves prioritizing project risks and assessing their probability and impact, which are key components of the Perform Qualitative Risk Analysis process. Option A focuses on identifying risks without prioritization, B is about sensitivity analysis, and C deals with numerical data analysis rather than qualitative assessment.